Maintenance and Servicing Works :

No.Project DescriptionClient
11 x 10tph watertube steam – Overhaul, service and inspection for certificate of fitness renewal.Golden Horse Rubber Sdn Bhd,
PKFZ, Port Klang, Selangor.
2Pressure vessels – Overhaul, service and inspection for certificate of fitness renewal.Golden Horse Rubber Sdn Bhd,
PKFZ, Port Klang, Selangor.
3Steam header insulation works.Golden Horse Rubber Sdn Bhd,
PKFZ, Port Klang, Selangor.
4Provided technical support for DOSH registration of Cefla s.c. autoclaveMedigate Sdn Bhd, Shah Alam, Selangor.
5Provided technical support for DOSH registration of Cefla s.c. autoclaveAR Dental Supplies Sdn Bhd, Shah Alam, Selangor.
6Provided visiting engineer (ICE) service for Sothern Power Generation Sdn Bhd (January 2020 – December 2020).GE Power Solutions (Malaysia) Sdn. Bhd., Pasir Gudang, Johor.
7Performed the Non-Destructive Testing (DPI and UTTG) at watertube steam boiler for Certificate of Fitness renewal. GAIA Carbon Sdn Bhd, Ulu Tiram, Johor.
8Performed the Hydrostatic Test (1,200 kPaG) at watertube steam boilerGAIA Carbon Sdn Bhd, Ulu Tiram, Johor.
9Performed the Non-Destructive Testing (DPI and UTTG) at firetube waste gas steam boiler for Certificate of Fitness renewal.GAIA Carbon Sdn Bhd, Ulu Tiram, Johor.
10Boiler repair (tube plugging) for watertube steam boilerGAIA Carbon Sdn Bhd, Ulu Tiram, Johor.
11Steam Distribution Pipe Design for Kilang Sawit Kechau BFGV Industries Sdn Bhd
12Steam Pipe Design for steam transfer from Evergreen Intermerge Sdn Bhd (Biomass Power Plant) to FGV Refineries Sdn BhdFGV Refineries Sdn Bhd
(Tawau Oil Products)
13Design, install and commissioning of a steam pipe from main header to the condensate pumpDanisco Malaysia Sdn Bhd
14Installation of Condensate Return PumpDanisco Malaysia Sdn Bhd
15Detailed Engineering Study on Flue Gas Diversion for Firetube BoilerSynthomer Sdn Bhd

Steam Plant Energy Management and Engineering Services
List of energy projects:

No.Project DescriptionClient
1

Steam Plant Optimization Project – Upgrading Pharmaniaga steam plant system.

–       Installation of Condensate Pump, Compact Module Thermodynamic Steam Trap (CMTD), steam flowmeters with flow indicator, moisture trap, Deaerator Head, Safety Relief Valve for steam header, and steam monitoring system.

Pharmaniaga LifeScience Sdn Bhd
Puchong, Selangor.
2Steam Plant Energy Optimization Study and Analysis Project.Eastman Chemicals (M) Sdn Bhd
3Steam Air Dyer and Process Heat Exchanger Improvement Study and Analysis Project.Gebeng, Kuantan, Pahang.
4Installation, testing and commissioning of 35 unit of venturi nozzle steam traps.Lynas Malaysia Sdn Bhd
Gebeng, Kuantan, Pahang
5Firetube Steam Boiler Efficiency StudySynthomer (Malaysia) Sdn Bhd,
Kluang, Johor.
6Preliminary Study on the Flue Gas Analysis on Waste Gas BoilerSynthomer (Malaysia) Sdn Bhd,
Kluang, Johor.
7Supply, Install, testing and Commission of three unit of venturi nozzle steam traps for Steam Back-Pressure Receiver (BPR) and main steam header at Kilang Sawit Kechau B, Kuala Lipis, Pahang.FGV Industries Sdn Bhd
8Suppy, Install, Testing and Commissioning of Venturi Nozzle steam traps for main steam header.Idemitsu SM (SM) Sdn Bhd
9Performed valve leaks test (384 units) at 2×220 MW Heat Recovery Steam Generator (HRSG).Southern Power Generation Sdn Bhd, (1,440 MW Power Plant) Pasir Gudang, Johor.
10Supply, Install, testing and Commission of new piping, valves and seven unit of venturi nozzle steam traps assembly within boiler system at Kilang Sawit Besout, Perak.FGV Industries Sdn Bhd