Maintenance and Servicing Works :
| No. | Project Description | Client |
| 1 | 1 x 10tph watertube steam – Overhaul, service and inspection for certificate of fitness renewal. | Golden Horse Rubber Sdn Bhd, PKFZ, Port Klang, Selangor. |
| 2 | Pressure vessels – Overhaul, service and inspection for certificate of fitness renewal. | Golden Horse Rubber Sdn Bhd, PKFZ, Port Klang, Selangor. |
| 3 | Steam header insulation works. | Golden Horse Rubber Sdn Bhd, PKFZ, Port Klang, Selangor. |
| 4 | Provided technical support for DOSH registration of Cefla s.c. autoclave | Medigate Sdn Bhd, Shah Alam, Selangor. |
| 5 | Provided technical support for DOSH registration of Cefla s.c. autoclave | AR Dental Supplies Sdn Bhd, Shah Alam, Selangor. |
| 6 | Provided visiting engineer (ICE) service for Sothern Power Generation Sdn Bhd (January 2020 – December 2020). | GE Power Solutions (Malaysia) Sdn. Bhd., Pasir Gudang, Johor. |
| 7 | Performed the Non-Destructive Testing (DPI and UTTG) at watertube steam boiler for Certificate of Fitness renewal. | GAIA Carbon Sdn Bhd, Ulu Tiram, Johor. |
| 8 | Performed the Hydrostatic Test (1,200 kPaG) at watertube steam boiler | GAIA Carbon Sdn Bhd, Ulu Tiram, Johor. |
| 9 | Performed the Non-Destructive Testing (DPI and UTTG) at firetube waste gas steam boiler for Certificate of Fitness renewal. | GAIA Carbon Sdn Bhd, Ulu Tiram, Johor. |
| 10 | Boiler repair (tube plugging) for watertube steam boiler | GAIA Carbon Sdn Bhd, Ulu Tiram, Johor. |
| 11 | Steam Distribution Pipe Design for Kilang Sawit Kechau B | FGV Industries Sdn Bhd |
| 12 | Steam Pipe Design for steam transfer from Evergreen Intermerge Sdn Bhd (Biomass Power Plant) to FGV Refineries Sdn Bhd | FGV Refineries Sdn Bhd (Tawau Oil Products) |
| 13 | Design, install and commissioning of a steam pipe from main header to the condensate pump | Danisco Malaysia Sdn Bhd |
| 14 | Installation of Condensate Return Pump | Danisco Malaysia Sdn Bhd |
| 15 | Detailed Engineering Study on Flue Gas Diversion for Firetube Boiler | Synthomer Sdn Bhd |
Steam Plant Energy Management and Engineering Services List of energy projects:
| No. | Project Description | Client |
| 1 | Steam Plant Optimization Project – Upgrading Pharmaniaga steam plant system. – Installation of Condensate Pump, Compact Module Thermodynamic Steam Trap (CMTD), steam flowmeters with flow indicator, moisture trap, Deaerator Head, Safety Relief Valve for steam header, and steam monitoring system. | Pharmaniaga LifeScience Sdn Bhd Puchong, Selangor. |
| 2 | Steam Plant Energy Optimization Study and Analysis Project. | Eastman Chemicals (M) Sdn Bhd |
| 3 | Steam Air Dyer and Process Heat Exchanger Improvement Study and Analysis Project. | Gebeng, Kuantan, Pahang. |
| 4 | Installation, testing and commissioning of 35 unit of venturi nozzle steam traps. | Lynas Malaysia Sdn Bhd Gebeng, Kuantan, Pahang |
| 5 | Firetube Steam Boiler Efficiency Study | Synthomer (Malaysia) Sdn Bhd, Kluang, Johor. |
| 6 | Preliminary Study on the Flue Gas Analysis on Waste Gas Boiler | Synthomer (Malaysia) Sdn Bhd, Kluang, Johor. |
| 7 | Supply, Install, testing and Commission of three unit of venturi nozzle steam traps for Steam Back-Pressure Receiver (BPR) and main steam header at Kilang Sawit Kechau B, Kuala Lipis, Pahang. | FGV Industries Sdn Bhd |
| 8 | Suppy, Install, Testing and Commissioning of Venturi Nozzle steam traps for main steam header. | Idemitsu SM (SM) Sdn Bhd |
| 9 | Performed valve leaks test (384 units) at 2×220 MW Heat Recovery Steam Generator (HRSG). | Southern Power Generation Sdn Bhd, (1,440 MW Power Plant) Pasir Gudang, Johor. |
| 10 | Supply, Install, testing and Commission of new piping, valves and seven unit of venturi nozzle steam traps assembly within boiler system at Kilang Sawit Besout, Perak. | FGV Industries Sdn Bhd |